The superconducting cavity development task will provide the fabrication and tests of fully equipped SC cavity prototypes and at the design, fabrication and test of a multipurpose cryomodule for the low energy section of the proton driver linac (also suitable for the post-accelerator). A test of the cryomodule with low intensity proton beam will be also performed.
TASK HOME
INTERNAL TASK NOTE
Eurisol-DS task 8 parameter database
29/03/2009 -Task : TASK 8
29/03/2009 -Task : TASK 8
Author(s) :S. Bousson
The document lists all the important parameters of the prototypes (cavities, power couplers and amplifier) beiing designed in the Eurisol-DS task 8 framework.
The document lists all the important parameters of the prototypes (cavities, power couplers and amplifier) beiing designed in the Eurisol-DS task 8 framework.
|
Download
[ 08-25-2009-0006]
( 36KB )
Study of the ceramic window geometry for HWR and Spoke cavity power coupler
29/03/2009 -Task : TASK 8
29/03/2009 -Task : TASK 8
Author(s) :C. Mielot
This document describes all the detailed comparison of several ceramic window design for fundamental power coupler meant to provide RF power to spoke or half wave superconducting cavities.
This document describes all the detailed comparison of several ceramic window design for fundamental power coupler meant to provide RF power to spoke or half wave superconducting cavities.
|
Download
[ 08-25-2009-0005]
( 2378KB )
Spoke Cavity Cold Tuning System
29/03/2009 -Task : TASK 8
29/03/2009 -Task : TASK 8
Author(s) :N. Gandolfo
This document reports on the conception and experimental results on the spoke cavity cold tuning system (in french)
This document reports on the conception and experimental results on the spoke cavity cold tuning system (in french)
|
Download
[ 08-25-2009-0003]
( 2703KB )
DELIVERABLES
D1 Cryostat design fabrication
No | Milestones and expected results of this task | Months due | Months achieved | Related documents |
D1 /M1.1 | Start cryostat fabrication | 13 | 12 | 08-25-2009-0009 |
D1 /M1.2 | Cryostat assembly | 29 | 24 | 08-25-2009-0017 |
D2 RF source development
No | Milestones and expected results of this task | Months due | Months achieved | Related documents |
D2 /M2.1 | First RF source | 17 | 15 | 08-25-2009-0004 |
D2 /M2.2 | Two additional 10 kW source fabricated | 36 | 49 | 08-25-2009-0011 |
D3 Spoke cavities study and fabrication (coupler & tuner)
No | Milestones and expected results of this task | Months due | Months achieved | Related documents |
D3 /M3.1 | Two spoke cavity achieved with tuner and coupler | 24 | 34 | 08-25-2009-0005 |
D3 /M3.2 | Third spoke achieved | 48 | 54 | 08-25-2009-0012 |
D4 HW resonators study and fabrication (coupler & tuner)
No | Milestones and expected results of this task | Months due | Months achieved | Related documents |
D4 /M4.1 | Two HWR fabricated and equipped with tuner and coupler | 28 | 34 | 08-25-2009-0005 08-25-2009-0013 |
D4 /M5.1 | Preparation of test bench for coupler conditioning | 22 | 51 | 08-25-2009-0015 |
D5 Cavity cold tests
No | Milestones and expected results of this task | Months due | Months achieved | Related documents |
D5 /M6.1 | Cold test of each spoke cavity | 50 | 50 | 08-25-2009-0007 |
D5 /M6.2 | Cold test of spoke cavity full equipped(coupler, tuner) | 52 | 51 | 08-25-2009-0016 |
D6 Cryomodule: preparation, assembly & test (w/o & with beam)
No | Milestones and expected results of this task | Months due | Months achieved | Related documents |
D6 /M7.1 | Cold test of a complete cryomodule | 36 | 51 | 08-25-2009-0019 |
D6 /M7.2 | Test with beam | 54 | 54 |
D7 Final report on cold and in-beam tests of the cryomodule