Coordination and overseeing of technical, scientific, contractual, financial and administrative activities. Coordination of knowledge management: protection, use and dissemination of EURISOL DS results.
TASK HOME
INTERNAL TASK NOTE
EURISOL Design Study Final Report
08/12/2009 -Task : TASK 1
08/12/2009 -Task : TASK 1
Author(s) :The EURISOL Management Board, Edited by J.C.Cornell
This is a browser-friendly PDF version of the Final Report of the EURISOL Design Study. 13 MBytes.
This is a browser-friendly PDF version of the Final Report of the EURISOL Design Study. 13 MBytes.
|
Download
[ 01-25-2009-0016]
( 13192KB )
D5 - Report on Cost Estimation
09/10/2009 -Task : TASK 1
09/10/2009 -Task : TASK 1
Author(s) :Management Team
Report on cost estimation of the proposed EURISOL facility
Report on cost estimation of the proposed EURISOL facility
|
Download
[ 01-25-2009-0015]
( 91KB )
D4 - Report of Facility Layout
09/10/2009 -Task : TASK 1
09/10/2009 -Task : TASK 1
Author(s) :Management Team
Report of Facility Layout, with drawings
Report of Facility Layout, with drawings
|
Download
[ 01-25-2009-0014]
( 944KB )
EURISOL Site Investigation Panel Report
15/03/2009 -Task : TASK 1
15/03/2009 -Task : TASK 1
Author(s) :Giacomo Cuttone (INFN-LNS), Don Geesaman (Argonne), Alex C. Mueller (IN2P3), Steve Myers (CERN) and Alan Shotter (TRIUMF/ Edinburgh; chair).
Report of the Site Investigation Panel
Report of the Site Investigation Panel
|
Download
[ 01-25-2009-0013]
( 1333KB )
Fourth Interim Report
26/11/2008 -Task : TASK 1
26/11/2008 -Task : TASK 1
Author(s) :Y. Blumenfeld and John Cornell
Fourth Interim Report covering the period 1/2/2008 to 31/10/2008
Fourth Interim Report covering the period 1/2/2008 to 31/10/2008
|
Download
[ 01-25-2008-0012]
( 7276KB )
DELIVERABLES
D1 Web site
No | Milestones and expected results of this task | Months due | Months achieved | Related documents |
D1 /M1 | Web site set up | 2 | 11 | 01-31-2006-0002 |
D1 /M2 | Web site maintenance | 57 | 24 | 01-25-2008-0010 |
D2 Monitoring of the work planning
No | Milestones and expected results of this task | Months due | Months achieved | Related documents |
D2.1 /M3.1 | Annual participant meeting and First year reports | 13 | 13 | 01-31-2006-0001 |
D2.2 /M3.2 | Annual participant meeting and Second year reports | 25 | 25 | 01-31-2007-0005 |
D2.3 /M3.3 | Annual participant meeting and Third year reports | 37 | 37 | 01-31-2008-0015 |
D2.4 /M3.4 | Annual report editing Fourth year | 48 | 48 | 01-31-2009-0016 |
D2.5 /M3.5 | Final participant meeting and final report editing | 54 | 59 | 01-31-2009-0023 |
D3 Report on site options
No | Milestones and expected results of this task | Months due | Months achieved | Related documents |
D3 /M4 | Conclusions of the investigation on site options | 48 | 48 | 01-25-2009-0013 |
D4 Report on facility layout
No | Milestones and expected results of this task | Months due | Months achieved | Related documents |
D4 /M5 | Finalization of facility layout | 52 | 57 | 01-25-2009-0014 |
D5 Report on cost estimation
No | Milestones and expected results of this task | Months due | Months achieved | Related documents |
D5 /M6 | Cost estimation | 54 | 57 | 01-25-2009-0015 |
D6 Final report on the whole Facility