TASK 6 - Heavy Ion Accelerator Design

eurisol ds
The Heavy Ion Accelerator task will provide an engineering oriented design of a CW linear post-accelerator for radioactive ion beams produced with the EURISOL facility. It will have the capability to accelerate light, medium and heavy ion beams up to 100 A.MeV. It will address the requirements for beam characteristics and distribution demanded by users. It will also examine ways to accommodate the requirements for beta-beam production.
TASK HOME
INTERNAL TASK NOTE
Fast chopper construction of prototype - Final report
15/07/2009 -Task : TASK 6
Author(s) :M. Di Giacomo G. Le Dem

This report is the deliverable D5/M6.2
Experimental Requirements - Beam and Machine Characteristics - Final Version
06/05/2009 -Task : TASK 6
Author(s) :N.Orr

This document presents the final version of the user requirements, as far as beam and machine characteristics are concerned
Experimental Requirements - Beams and Machine characteristics
03/11/2006 -Task : TASK 6
Author(s) :Nigel ORR

This note presents the user requirements for the EURISOL post-accelerator
Preliminary analysis for the HF Chopper solutions
03/11/2006 -Task : TASK 6
Author(s) :Marco DI GIACOMO Gwenal LE DEM

This note presents a preliminary analysis of the different solutions for the HF chopper for EURISOL post-accelerator
Normal conducting Injector
03/11/2006 -Task : TASK 6
Author(s) :Alexander BECHTOLD

This report presents the different studies held in the frame of the Normal Conducting Injector for the EURISOL post-accelerator
DELIVERABLES

D1 Beam dynamics calculation
No Milestones and expected results of this task Months due Months achieved Related documents
D1/M1 User specifications      
D1 /M1.1 Preliminary specifications for beam dynamics 6 6 06-25-2006-0004
D1 /M1.2 Final specifications for beam dynamics 17 16 06-25-2009-0011
D1/M2 Beam dynamics simulation      
D1 /M2.1 Preliminary design and cavity definition 6 20 06-25-2006-0001
D1 /M2.2 Detailed accelerator design 45 45 06-25-2009-0022

D2 Development of normal conducting structures
No Milestones and expected results of this task Months due Months achieved Related documents
D2 /M3.1 Assembly of the test beam line 6 6
D2 /M3.2 Development of RF system 15 18
D2 /M3.3 Beam measurements 42 46 06-25-2009-0016

D3 Comparison of NC and SC RFQ
No Milestones and expected results of this task Months due Months achieved Related documents
D3 /M4.1 Test of the LNL SC FRQ 6 15 06-25-2009-0014
D3 /M4.2 Engineering design revised 37 47 06-25-2009-0015
D3 /M4.3 Comparison of NC and SC RFQ 37 53 06-25-2009-0023

D4 Development of RIB beam diagnostics
No Milestones and expected results of this task Months due Months achieved Related documents
D4 /M5.1 Design preparation 37 37 06-25-2009-0020
D4 /M5.2 Construction of prototype 42 42 06-25-2009-0021
D4 /M5.3 Beam test of prototype 48 52 06-25-2009-0021

D5 Design and development of high frequency chopper
No Milestones and expected results of this task Months due Months achieved Related documents
D5 /M6.1 Design preparation 12 24 06-25-2007-0008
D5 /M6.2 Construction of prototype 48 53 06-25-2009-0017
D5 /M6.3 Beam test 54 54 06-25-2009-0018

D6 Final report on task activities
INVOLVED INSTITUTIONS